| 01 | General conditions, mobilization | $88,000 | CLEAR | Administrative line; no product scope to match |
| 02 | Selective demolition — mech & elec | $64,000 | CLEAR | No submittal-governed product; billed within schedule |
| 03 | Ductwork, dampers, accessories | $176,400 | CLEAR | Consistent with approved 23-31-00-B (SMACNA) |
| 04 | Energy recovery units | $214,000 | CLEAR | Billed equipment matches approved 23-72-23-A, basis of design |
| 05 | Hydronic piping mains & runouts | $136,800 | CLEAR | Consistent with approved 23-21-13-A |
| 06 | Pipe insulation & jacketing | $46,400 | CLEAR | Partial billing; no approved-document conflict |
| 07 | Vibration isolation, seismic | $24,000 | CLEAR | No conflict on documents provided |
| 08 | DX split system AHU-1 / CU-1 | $88,000 | FINDING 01 | Billed York/AHRI 430-435 spec unit; approved record is residential Goodman |
| 09 | Refrigerant piping + coil connections | $22,000 | FINDING 02 | Coil-connection scope absent from approved equipment |
| 10 | BAS / BACnet controls integration | $60,800 | CLEAR | Progress billing consistent with approved 26-05-83-A |
| 11 | Condensing unit pad, 4500 PSI | $9,000 | CLEAR | Matches approved mix design 03-30-00-A |
| 12 | Testing, adjusting, balancing | $19,000 | CLEAR | 50% progress billing; no conflict |
| 13 | Closeout, O&M, training | $0 | CLEAR | Not yet billed |